Before you begin
For each fail-open configuration, you will need to make sure you have all these components.
- Determine the IP address for the fail-open switch or, if you are deploying multiple switches, a range of IP addresses
- Determine a network mask and the default gateway for the fail-open switch
- 4 cables to connect the fail-open switch and the Sensor
- (Optional) A DB-9 RS232 female-female cable to access the fail-open switch CLI
- 2 SFPs, XFPs, or QSFPs for the fail-open switch and 2 SFPs, XFPs, or QSFPs for the Sensor
- Cables for a copper fail-open switch
- 2 CAT5e cables (1 cross-over, 1 straight-through) for network ports
- 2 CAT5e cables (straight-through) for monitor ports
- Cables for a fiber fail-open switch
- 2 LC fiber cables for network ports
- 2 LC fiber cables for monitor ports
- 1 control cable if you are connecting a passive fail-open switch
Broadly, these are the steps you will need to follow to set up a fail-open kit.
Task
- Install the fail-open switch.
- (Optional) Configure bypass switch parameters.
- (Optional) Configure notification by SNMP traps
- Cable bypass switch to a Sensor using the appropriate cables.
- Configure Sensor ports as inline fail-open.
- (Optional) Use the Web Manager to configure the fail-open switch settings.